Kitchen floor and wall material removed ahead of an alteration permit on a ranch house
Example project
- Home
- 1960s ranch house in Carson with vinyl over the kitchen floor and textured, taped walls
- Original request
- Remodel the kitchen and move a doorway, under an alteration permit from LA County Building and Safety
- Testing
- A Cal/OSHA-certified asbestos consultant samples the vinyl and the glue under it, the wall texture and the taped joints
- Found
- Asbestos in the vinyl and glue and in the taped joints
- Clear
- The wall texture
- Area
- About 150 sq ft of kitchen floor and wall
- Timeline
- Notice no later than 10 working days ahead, then three working days
- Cost
- $4,300
Scope of work
The kitchen sealed with air filters running, the positive vinyl, glue and joint compound removed wet, bagged disposal and a cleanup. The survey, the district notification fee, the clearance air test, the carpentry and the new floor are separate.
Project overview
In this example, the owners of a 1960s ranch house in Carson are remodeling the kitchen. LA County Building and Safety provides the building services, and its permit form carries a box for the asbestos notification, or a declaration that notification does not apply.
The vinyl, its glue and the taped joints test positive, so notification applies. The abatement contractor files the notice online, a copy goes in with the permit papers and the abatement crew finishes before the carpenter starts.
The goal
The goal is a kitchen with the positive materials gone and the permit papers in order before the carpenter starts.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the floor and the walls.
- Before work The abatement contractor files the district notice online, and a copy goes in with the county permit papers.
- Days one to three The kitchen is sealed and the vinyl, glue and compound come out wet.
- Last An independent consultant tests the air, then the carpenter moves the doorway.
Planning right
- Ask the county counter which forms go with the alteration permit.
- Keep the notice with the permit set.
- Empty the lower cabinets and the pantry.
- Choose the floor while the notice is pending.